Posts

Showing posts from February, 2021

Appleton City Sidewalk - 2/5/2021

Image
Forms are set and base compacted for today’s concrete pour. Sidewalk installed earlier in the week still blanketed. Concrete tested out good and the pour is underway. Guys have the truncated domes in and are smoothing out the surface. The pour is complete and all went well. The main crew has removed more existing sidewalk today as well as compacted the base. Guys finishing up smoothing out the surface of the new sidewalk. Another view of our next section that will be replaced.

Appleton City Sidewalk - 2/3/2021

Image
View of the new concrete poured yesterday. Laying down base for the new sidewalk. Base compacted and ready for concrete. Getting forms set up for new sidewalk. View of the depth change for driveways. Concrete pour underway. Guys getting things smoothed out. Second pour of the day.