Appleton City Sidewalk - 3/16/2021



Prepping the forms at the school for a concrete pour.


Cut the asphalt 8’ wide to adjust for a compliant cross slope. 5’ sidewalk. New asphalt on each side.


Forms are set and ready for the pour.


First truck is underway. Tested out good.


Smoothing out the surface of the concrete. Second truck was denied because it was too wet.


Third truck is good and the guys continue the pour.


Fourth and final truck finishing out the pour.


Pour is complete, just have to smooth things out.