Appleton City Sidewalk - 4/2/2021

Image
East side of Maple at the 4th street intersection. 5th Street intersection looking north. North end of the job looking south. Area that has had dirt work completed.  Just south of the school looking north. Main crew working on dirt work south of the school. Seeding and asphalt next week.

Appleton City Sidewalk - 4/1/2021

Image
Guys getting some bridge connections prepped for a pour today. A look at one of the problem areas we had. Guy wire went right where our new sidewalk was supposed to go so the engineers decided to go around the pole. Extended the storm pipe to daylight on the south end. View from the north looking south toward 4th street. Dirtwork being done by the main crew. A look at the new sidewalk down by the pool.

Appleton City Sidewalk - 3/30/2021

Image
Getting forms set up for the concrete pour. Pour is underway. Section by the pool. Section just south of the school. Section on west 4th street. Pour completed. All went well.

Appleton City Sidewalk - 3/24/2021

Image
Discussed the bridge by the school with the contractor and the engineer. The last driveway at the school has been tore out and rock is awaiting compaction. Discussed the bridge at the 4th street intersection with contractor and engineer. Crew is digging out the location of the last bridge on the west side of 4th street.

Appleton City Sidewalk - 3/22/2021

Image
The subcontractor is getting relief cuts in all the sidewalk south of 4th Street. Rock was added to a few driveways. Needed redone after some of the rains had washed out the original. School is back in session and the driveways are open for full access. We will come back and fill this gap with asphalt at a later date.

Appleton City Sidewalk - 3/18/2021

Image
The guys have added rock between the asphalt and the new sidewalk at the school allowing access for class that resumes on Monday. Picked up cylinders and delivered to PPI.