The guys have added rock between the asphalt and the new sidewalk at the school allowing access for class that resumes on Monday. Picked up cylinders and delivered to PPI.
Discussed the bridge by the school with the contractor and the engineer. The last driveway at the school has been tore out and rock is awaiting compaction. Discussed the bridge at the 4th street intersection with contractor and engineer. Crew is digging out the location of the last bridge on the west side of 4th street.
Digging out the old rock and getting the base compacted at the school. First layer of asphalt in and compacted. Top layer in and getting rolled. Working their way south. Getting new asphalt laid at the mayor’s drive. Finished product at the school.
Prepping the forms at the school for a concrete pour. Cut the asphalt 8’ wide to adjust for a compliant cross slope. 5’ sidewalk. New asphalt on each side. Forms are set and ready for the pour. First truck is underway. Tested out good. Smoothing out the surface of the concrete. Second truck was denied because it was too wet. Third truck is good and the guys continue the pour. Fourth and final truck finishing out the pour. Pour is complete, just have to smooth things out.
Comments
Post a Comment