Appleton City Sidewalk - 3/4/2021



Maple & 4th Street intersection ready for concrete.






Main crew working on digging up existing sidewalk down near the pool. 


Section on Maple Avenue ready for concrete.


Job board inspection completed.


Replacing the pole that was accidentally hit and damaged by the construction crew.


The concrete plant informed us that they would not be able to get us concrete today and it has canceled our pour. They will pour tomorrow and collect their own cylinders.