Appleton City Sidewalk - 3/8/2021



Sidewalk crew removing the forms and making cuts in the new concrete at the intersection of 4th and Maple.


This pour was done on Friday. Delivering cylinders to PPI today.


New concrete looks good.


Also poured the first 3 bridges.


Intersection of Maple and 5th street.


Main crew continuing to remove the old sidewalk on Maple south of the school.


Sidewalk crew getting forms set up down near the pool for a concrete pour tomorrow.